When we arrived at the house today to await the representative from Efficiency Vermont to do the thermal bypass inspection. What we found was that the front door was installed and the drywall installers were busy putting up the rock.
Hummmmm. I didn't think that was supposed to happen until Thursday. The thermal bypass inspection was to happen before the drywall was installed. As it was it worked out quite well. Lindsay from Efficiency Vermont and proceeded to look things over. She took a lot of notes and said that everything on the main floor were ok. However when we got to the basement and told here that we were not going to finish it now she said that to get our energy star rating and our rebates we needed to put sheetrock on the exterior walls. So we now have a task for next year. The project will be kept open and when we get the walkout basement perimeter walls sheetrocked we can get the final inspection and incentives next year.
All in all I think the inspection went quite well.