Tuesday, September 01, 2009

Moving along on the house

Yesterday the floor and rim joists were set, some grading was done and some caulking along the rim joist.

Today the subfloor decking was installed and the lumber was delivered to begin the wall construction and sheeting. I did more caluking of the rim joist and will finish that tomorrow or Thursday.

During the lunch break we went over the calendar so we knew when to have the appliances, flooring, can lighting delivered. The plan is to be ready for the plumber by 9/9, electrician by 9/14, insulation 9/16, dry wall paint and trim begins the week of 9/21 with floor covering beginning the following week. So it looks like completion will be mid October. Wow, they have an aggressive schedule. The next couple of weeks look like GOOD, no rain, weather.

Today's and yesterday's pictures.

No comments: